Highway 24 and Green Valley Road Construction Update 6-15-22

5-20-2022:

The left eastbound and westbound lanes of Highway 24 have been reopened. The full length of one of the left turn lanes for eastbound Highway 24 at Green Valley Road has been opened as well.

Traffic on Green Valley Road has been shifted onto the new lanes between Grouse Circle and Highway 24. Green Valley Road remains open to traffic in both directions, however, the right northbound lane of Green Valley Road will remain closed to traffic with cones directing traffic through the work zone. This lane closure is to allow for work along the east side of Green Valley Road.

The traffic light cycles will be refined in the next 2 weeks as the remainder of the signal devices are installed.

_________________________________________

Beginning Monday, March 21, 2022, Highway 24 will be reduced to one lane in each direction. The left lanes of both eastbound and westbound Highway 24 will be closed from Scottie Lane to Green Valley Parkway (entrance to the business park).

The lanes are being closed to allow for work to install a storm sewer in the median and construct dual left turn lanes for eastbound Highway 24 at Green Valley Road.

A left turn lane for eastbound Highway 24 at Green Valley Road will be provided during this phase of construction.

This phase of construction is expected to be completed in 6 weeks, weather permitting.

Facebook Twitter Email

Latest Update:

June 16, 2022 2:08 PM

Here is a summary of work that has been completed and items that remain on the Green Valley Road project.

The existing eastbound Highway 24 left turn lane has been lengthened and an additional eastbound left turn lane has been created, although it is not yet open.

Highway 24 median work has been completed, however, there is an issue with ponding. Designers are working on a solution to be completed prior to opening the inside eastbound left turn lane.

The westbound Highway 24 right turn lane into Farmers Drive has been completed.

The frontage road behind Farmers State Bank and Prairie Hawg Cycle & Leather has been completed and is open to traffic.

Dempsey Road has been overlaid and will receive final pavement markings at the same time Green Valley Road pavement markings are installed.

Final programming of the traffic signals is dependent on the pedestrian portion of the signals being installed.  The pedestrian portion includes push button stations installed on bases that mount on sidewalks that are not yet installed.

The contractor’s schedule for other projects affects their time on the Green Valley project but they anticipate completing this work in July.

The contract has a final completion date of August 1, 2022, after which the contractor would incur liquidated damages.


Prior Updates

May 18, 2022 3:52 PM

Buried utility conflicts, theft of materials, and weather delays has pushed the anticipated completion of work on Highway 24 back to June 3rd.